Bulgarian State Railways began regular operation with its first two Coradia Stream EMUs on 1 September 2026, after 12 of the 35 ordered units had reached Bulgaria.

A Bulgarian Coradia Stream EMU in green-and-white BDZ livery at a station platform
An official image published on 31 August 2026 shows a Bulgarian Coradia Stream EMU in BDZ livery at a station platform. Photo: Bulgarian State Railways (BDZ).

BDZ assigned the two units mainly to four routes at launch: Plovdiv–Svilengrad, Plovdiv–Asenovgrad, Svilengrad–Sofia and Sofia–Pernik. The operator scheduled the first journey to leave Plovdiv at 05:30 for Svilengrad. Further routes will be added as more units are delivered and enter service.

Service began with two of 12 delivered units

The delivery figure dates from 25 August, when the ministry presented the first unit from the new Bulgarian fleet at Sofia Central station. Transport and Communications Minister Georgi Peev said twelve trains had reached Bulgaria and that the remaining 23 would be ready for delivery by April 2027. The ministry and BDZ announcements did not give a date for putting the other ten delivered units into passenger service.

Meanwhile, eight Škoda RegioPanter EMUs entered regular service on 14 August. The ministry said the operating fleet was expected to reach 20 units by 20 August and credited the launch to accelerated administrative, certification and training work. Bulgaria’s full Škoda programme covers 25 trains: an initial 20-unit order and five additional units. Together with the 35 Alstom units, the two programmes cover 60 trainsets. Peev separately said that 280 to 300 passenger carriages were strategically required, a figure that is not directly comparable with the number of trainsets.

Bulgaria’s two new EMU fleets on their first day of regular service, August–September 2026
Fleet Units under contract In regular service on the first day First day of service
Alstom Coradia Stream 35 2 1 September 2026
Škoda RegioPanter 25 8 14 August 2026
Bulgarian State Railways opened Coradia Stream service with 2 units out of the 12 already delivered. The Škoda launch started with 8 units, and the ministry expected the operating fleet to reach 20 by 20 August. Sources: Bulgarian State Railways; Ministry of Transport and Communications, 25 August 2026; Ministry of Transport and Communications, 14 August 2026.

What the BULEMU contract covers

Alstom leads the BULEMU consortium. Its Bulgarian partner RVP Invest provides the maintenance facility. The consortium signed the contract with the Ministry of Transport and Communications in April 2025. The package is worth €720 million in total, and Alstom itself takes €600 million. Specifically, the rolling stock accounts for €452 million and the 15-year maintenance package for €268 million.

Second-class passenger saloon inside a Bulgarian Coradia Stream EMU
An official image published on 31 August 2026 shows the second-class passenger saloon inside a Bulgarian Coradia Stream EMU. Photo: Bulgarian State Railways (BDZ).

Each trainset has six cars and runs at up to 160 km/h. The operator lists 325 first- and second-class seats and a fully low-floor layout. Ramps serve passengers with reduced mobility. Air conditioning, power sockets, USB ports, video surveillance and digital passenger counting also feature. The operator lists provision for wireless internet as well. Alstom in addition specified the units for ERTMS Level 2 and for journeys of up to four or five hours.

Bicycle storage area with securing straps inside a Bulgarian Coradia Stream EMU
An official image published on 31 August 2026 shows the bicycle storage area inside a Bulgarian Coradia Stream EMU. Photo: Bulgarian State Railways (BDZ).

Recovery funding supports the service-entry units

BDZ says the first Coradia Stream units placed in service were delivered under a contract financed through Bulgaria’s Recovery and Resilience Plan. At the August presentation, Deputy Prime Minister Atanas Pekanov said work on Bulgaria’s Social Climate Plan would continue over the following three months. He said the country expected around €3 billion under the plan, with a significant share intended for transport and energy efficiency. The ministry’s announcement did not explicitly link that funding to the remaining 23 Coradia Stream units.

Alstom Europe Region President Andrew DeLeone described the maintenance arrangement. The consortium will work from a depot built for the purpose in Bulgaria. Roughly 50 engineers and other Bulgarian staff will run it. Peev, for his part, wants the fleet on longer corridors as well, including the line to Burgas. BDZ says it will deploy the trains on more routes as further units arrive and enter service.

Coradia Stream programme in Bulgaria: from contract signature to service, April 2025 to April 2027
Date Step
April 2025 BULEMU consortium signs the 35-unit order with the Ministry of Transport and Communications
14 August 2026 First eight Škoda RegioPanter units start regular passenger work
25 August 2026 Ministry reports 12 Coradia Stream units in Bulgaria and presents the first one in Sofia
1 September 2026 Two Coradia Stream units begin commercial service on four routes
By April 2027 Alstom due to have the other 23 units ready for delivery
Sixteen months separate the order from the first passenger run, and the remaining 23 units are due to be ready for delivery by April 2027. Sources: Alstom; Ministry of Transport and Communications, 14 August 2026; Ministry of Transport and Communications, 25 August 2026; Bulgarian State Railways.