Chennai Metro Advances with Bids for ARE04A Rolling Stock Contract
26.01.2025
Chennai Metro Attracts Three Major Bids for ARE04A Rolling Stock Contract. This was reported by the railway transport news portal Railway Supply.

The Chennai Metro has taken a significant step forward with its Phase 2 development. Alstom, BEML, and Titagarh Rail Systems have submitted bids for the crucial ARE04A contract.
Don’t miss…Louisville Identified as Potential Amtrak Stop in New Federal Rail Study
Initial Challenges in the Tender Process
In November 2021, CMRL issued its first tender for 12 three-coach trains, intended for a 39-year operational span. However, only Titagarh Wagons bid, and their submission was rejected due to non-compliance. This led to the suspension of the tender, prompting CMRL to revise its procurement strategy for better results.
Chennai Metro’s New Approach to Procurement
Reissuing the tender in February 2024, CMRL successfully drew bids from Alstom, BEML, and Titagarh. This marks a milestone for the Chennai Metro as it refines its procurement process to meet growing urban mobility demands.
Specifications and Scope of the ARE04A Package
The contract includes the design, manufacturing, and delivery of 32 new train sets. Each three-coach train will accommodate 980 passengers and achieve speeds of up to 90 km/h. The project also involves testing, commissioning, personnel training, and a 15-year comprehensive maintenance agreement.
Train Delivery Schedule and Deadlines
The contractor must meet strict deadlines, delivering a prototype within 630 days and completing all batches in three years. This schedule ensures timely deployment of trains for Phase 2 operations.
Key Technical Features of the Trains
The trains will operate on standard-gauge tracks in a DMC+TC+DMC configuration, with maintenance at depots in Madhavaram, Semmancheri, or Poonamallee. Designed for efficiency and capacity, they will enhance commuter experience significantly.
Next Steps for ARE04A Contract Evaluation
The bids from Alstom, BEML, and Titagarh are undergoing technical evaluation. Once complete, financial bids from qualified contenders will be reviewed to select the most cost-effective solution.
Chennai Metro’s Vision for Urban Mobility
By improving its procurement approach and attracting top bidders, the Chennai Metro is committed to providing efficient and reliable public transportation. The success of Phase 2 will mark a transformative chapter for urban mobility in Chennai.
Source: metrorailnews.in
News on railway transport, industry, and railway technologies from Railway Supply that you might have missed:
Don’t miss…Transforming Transportation with African High-Speed Rail
Find the latest news of the railway industry in Eastern Europe, the former Soviet Union and the rest of the world on our page on Facebook, Twitter, LinkedIn, read Railway Supply magazine online.Place your ads on webportal and in Railway Supply magazine. Detailed information is in Railway Supply media kit