The UK government has launched a full-scale reset of the HS2 project after new evidence revealed how billions of pounds were misspent. This is reported by the railway transport news portal Railway Supply.

The UK government has launched a full-scale reset of the HS2 project after new evidence revealed how billions of pounds were misspent.
Photo: HS2

A recent Sunday Times investigation uncovered details showing contractors, consultants, and legal firms received massive payouts, even after large sections of the rail line were cancelled. The revelations ignited renewed criticism, triggering what many now call the HS2 cost scandal.

Don’t miss…Very Light Rail Innovation Centre enters crisis

The original vision for HS2 included high-speed rail links from London to Birmingham, Manchester, and Leeds. But after the northern phases were scrapped in 2023, only the London–Birmingham segment remains. That shortened route alone now carries an estimated cost of over £80 billion ($102 billion), with completion pushed back to the late 2030s. Global observers have cited the project as a cautionary example of poor infrastructure execution.

Billions Paid Despite Cuts and Delays

According to the report, HS2 Ltd has already spent £38.8 billion ($49.5 billion) on construction and another £3.8 billion ($4.85 billion) on property. Major contractors like Balfour Beatty and Vinci received more than £5 billion ($6.4 billion) each. Thirteen firms in total collected over £1 billion ($1.3 billion) under controversial “cost-plus” contracts, which guaranteed profits regardless of actual costs.

This funding model placed the financial risk squarely on the government and left little incentive for cost control. A senior government insider admitted that the contract structure made overspending almost inevitable. Legal fees reached £67 million ($85.6 million), while accounting giants charged £292 million ($373 million) for consulting. Public relations and stakeholder engagement consumed an additional £50 million ($64 million).

Political Shake-Up and New Leadership

Transport Secretary Heidi Alexander condemned the financial mismanagement as “an appalling mess” and promised to renegotiate contracts. She confirmed that the government would implement all 89 recommendations from a recent review led by infrastructure expert James Stewart. These include tighter spending rules, clearer accountability, and stronger penalties for overruns. “The days of blank-cheque projects are over,” Alexander said.

To lead the reset, former TfL Commissioner Mike Brown will chair HS2 Ltd. At the same time, the Department for Transport plans to strengthen oversight and eliminate political interference. The review also criticized years of weak coordination and scope creep that undermined cost control from the beginning.

Global Lessons from the HS2 Cost Scandal

This high-profile infrastructure failure offers serious lessons for governments worldwide. The HS2 cost scandal underscores the dangers of poor governance, risk misallocation, and lack of fiscal discipline. Although the UK hopes HS2 can still ease pressure on southern rail lines, its credibility has taken a major hit. For future megaprojects, one lesson stands out: deliver smarter, not just bigger.

Source: www.railtech.com

News on railway transport, industry, and railway technologies from Railway Supply that you might have missed:

Find the latest news of the railway industry in Eastern Europe, the former Soviet Union and the rest of the world on our page on Facebook, Twitter, LinkedIn, read Railway Supply magazine online.

Place your ads on webportal and in Railway Supply magazine. Detailed information is in Railway Supply media kit