First Amtrak Airo trains enter service two years after 2024 delivery target
Amtrak Airo trains entered passenger service on the Amtrak Cascades route on 30 September 2026, two years after the 2024 date Siemens Mobility set in 2021 for first deliveries.

Two trainsets now cover four daily trips on the route linking Vancouver, B.C., Seattle, Portland and Eugene. Amtrak, the Federal Railroad Administration (FRA) and Siemens Mobility all describe it as the first Airo passenger service in the United States. Each set has more than 300 seats.
The four Cascades trips now running Airo sets
Train 503 runs from Seattle to Eugene and Train 508 makes the return trip. Train 516 links Seattle with Vancouver, B.C., and Train 519 comes back. Amtrak marks these departures with a “New Train” tag on Amtrak.com and in its app. The other six Cascades trainsets are due to enter service through early 2027, and the Airo fleet will eventually replace the equipment now on the route. Amtrak’s Cascades order also covers two new locomotives and a spare cab car.
| Train | From | To | Departs | Arrives |
|---|---|---|---|---|
| 503 | Seattle | Eugene | 7:10 a.m. | 1:48 p.m. |
| 508 | Eugene | Seattle | 4:30 p.m. | 10:50 p.m. |
| 516 | Seattle | Vancouver, B.C. | 8:30 a.m. | 12:30 p.m. |
| 519 | Vancouver, B.C. | Seattle | 4:45 p.m. | 9:10 p.m. |
The two Airo trainsets cover one daily Seattle–Eugene round trip and one daily Seattle–Vancouver, B.C. round trip. Times are local, as published by Amtrak for the launch. Source: Amtrak, September 2026.
The corridor lost seats in late March 2025, when Amtrak grounded its Horizon cars. The Washington State Department of Transportation (WSDOT) says the Amfleet cars brought in as replacements reduced seating capacity by 20% for the rest of the year. Ridership fell 8% to 916,000 in 2025.

From the 2021 order to the first passengers
When Siemens Mobility announced its Amtrak contracts in July 2021, it said the first trains would be delivered in 2024. Deliveries for the Northeast Corridor and state-supported routes were to run from 2024 through 2030. None of the statements issued on 30 September explains the gap between that delivery date and the 2026 start of passenger service. In February 2026 Amtrak said all eight Cascades sets were expected to finish manufacturing during the year.
The national programme has also grown. The 2021 announcement covered 73 trains, while Siemens now puts the Airo programme at 83 trainsets, comprising 86 Charger locomotives and 576 passenger coaches. The trains are built at Siemens Mobility plants in Sacramento, California, and Lexington, North Carolina.
| Milestone | Date | Status |
|---|---|---|
| First Airo deliveries | 2024 | Date given by Siemens Mobility in July 2021 |
| Northeast Corridor and state-supported route deliveries | 2024 to 2030 | Schedule given by Siemens Mobility in July 2021 |
| Manufacturing of all eight Amtrak Cascades sets | 2026 | Amtrak expectation, February 2026 |
| Passenger service on Amtrak Cascades, two sets | 30 September 2026 | Started |
| Remaining six Amtrak Cascades sets | Through early 2027 | Planned |
| King Street Yard maintenance facility, Seattle | 2027 | Planned completion, Amtrak, May 2025 |
| Northeast Regional service | Late 2027 | Planned, first set in testing |
| Northeast Regional and other state-supported routes | Through 2030 | Planned, Siemens Mobility, September 2026 |
Passenger service on Amtrak Cascades began two years after the 2024 delivery date set in 2021, while the 2030 end point is unchanged. Delivery dates and service dates are separate milestones. Sources: Siemens Mobility, July 2021, Amtrak, February 2026, Amtrak, May 2025, Amtrak, September 2026, Siemens Mobility, September 2026.
Seattle maintenance base for the Airo sets
Amtrak is also building a maintenance base for the new trains at its King Street Yard in Seattle. In May 2025 the company said the upgraded yard, with a two-bay maintenance and inspection building and a separate service and cleaning bay, would be completed in 2027. Amtrak runs each Airo as a single trainset rather than as separate railcars. It said the new facilities would give it a consistent maintenance system with shorter turnaround times for repairs and inspections. At that point, six Amtrak yards were in line for similar work: construction was under way in Seattle and Philadelphia, with the other four yards at the contract, procurement or planning stage.
Northeast Regional is next, in late 2027
The first Airo trainset for the Northeast Regional has completed production and started testing, and Amtrak plans to launch service there in late 2027. In February, Amtrak gave 2027 as the expected start. Siemens says further trainsets will reach the Northeast Regional and other state-supported routes through 2030. Those trains will carry Amtrak’s national red, white and blue livery, while the Cascades sets wear the route’s evergreen, cream and mocha colours.
FRA says the fleet is supported by $3.5 billion of its investments. FRA Administrator David Fink, who previewed the trains with Amtrak on the weekend before the launch, set out what the agency expects from them:
“…this new fleet will substantially reduce maintenance downtime and eliminate delays for passengers.”